Austin foundation repair permits: what City records show and what they leave out
By Slab & Pier
Researched with AI help and checked against the sources listed at the end
Sources checked October 12, 2026.
At a glance
The City of Austin issued 10,361 residential repair permits that mention the foundation from January 2009 through September 2026. 2025 had the most of any full year, 740, and January to September 2026 had 760, the most for those months since 2009. Most closed permits end Final: 86.2% of those issued in 2024 and 2025. An expired permit does not show whether the work was done or how well. The records leave out work done without a permit, including small repairs the City exempts from a building permit. Since 2022, about 95% of permits list a reported valuation of exactly $1, so a permit's dollar figure does not show what a homeowner paid. This page names no company.
Do you need a permit for foundation repair in Austin?
For one- and two-family homes and townhouses of up to three stories, the City of Austin lists a foundation repair that does not exceed 128 square feet as work exempt from a building permit. Its Express Permits page lists foundation repair that does not add more than 128 square feet of impervious cover and says it issues most Express permits in one business day. Before 2019, no more than one permit a year in this study had a description beginning with the word Express; in 2019, 62 did, in 2020, 404, and from January to September 2026, 739 of 760.
The City's residential fee schedule for fiscal year 2026-27 lists a flat fee of $112.76 for Express residential plan review. That fee is separate from what the repair costs. Our Austin cost page lists the City fee items we found and the prices companies publish.
This study covers City of Austin permits only. For San Antonio, Fort Worth and Round Rock, our questions guide covers who pulls the permit and each city's engineer requirement for foundation repair permits.
How many foundation repair permits does Austin issue?
We counted residential building permits in the City's Repair work class whose description mentions the foundation, issued from January 1, 2009 through September 30, 2026: 10,361 permits. We call them foundation repair permits on this page. The match is by word, so a few describe other work: of 30 drawn at random from 2009 to 2020, 28 described foundation repair, one described plumbing work through the slab and one described exterior veneer damaged by an earlier foundation repair.
From 2009 through 2023, the City issued an average of 552 a year, from 404 in 2009 to 703 in 2012. In 2025 it issued 740, the most of any full year since 2009 and 28.2% more than the 577 in 2024. From January to September 2026 it issued 760, up 45.6% from 522 in the same months of 2025 and above the previous high for those months, 540 in 2012.
These are counts of permits issued, so they leave out work done without a permit.
The counts include 408 permits later marked void, withdrawn, cancelled or aborted. The third column leaves them out.
| Year | Permits issued | Issued, excluding void, withdrawn, cancelled and aborted | Issued January to September |
|---|---|---|---|
| Full year 2009 | 404 | 346 | 275 |
| Full year 2010 | 482 | 435 | 364 |
| Full year 2011 | 599 | 545 | 446 |
| Full year 2012 | 703 | 671 | 540 |
| Full year 2013 | 576 | 545 | 451 |
| Full year 2014 | 626 | 602 | 467 |
| Full year 2015 | 574 | 553 | 436 |
| Full year 2016 | 569 | 547 | 434 |
| Full year 2017 | 592 | 580 | 434 |
| Full year 2018 | 555 | 539 | 428 |
| Full year 2019 | 505 | 490 | 368 |
| Full year 2020 | 426 | 412 | 337 |
| Full year 2021 | 553 | 541 | 419 |
| Full year 2022 | 517 | 503 | 377 |
| Full year 2023 | 603 | 592 | 457 |
| Full year 2024 | 577 | 570 | 414 |
| Full year 2025 | 740 | 733 | 522 |
| 2026 to September | Year not complete | Year not complete | 760 |
What does a permit's status show?
On October 11, 2026, the 10,361 permits were marked Final (8,434), Expired (1,359), Withdrawn (207), Void (198), Active (157), Pending Permit (3), Cancelled (2) or Aborted (1). Every Final permit carries a completion date.
We count a permit as closed when it is Final or Expired. Most closed permits are Final, in every period below.
| Issued | Final share of closed permits | Final within 365 days of issue |
|---|---|---|
| 2009 to 2020 | 87.7% (5,491 of 6,264) | 80.1% (5,294 of 6,611) |
| 2021 to 2023 | 75.8% (1,237 of 1,631) | 72.2% (1,208 of 1,673) |
| 2024 to 2025 | 86.2% (1,119 of 1,298) | 82.7% (931 of 1,126) |
The last column counts Final permits completed within 365 days of issue, out of every permit issued at least 365 days before October 11, 2026, void and withdrawn permits included.
The lowest single year was 2022: 357 of its 503 closed permits were Final (71.0%) and 146 Expired. The records do not explain the lower shares for 2021 to 2023, and this page does not suggest a reason.
We leave 2026 out of this comparison because its permits have had less time to close: of the 760 issued from January to September 2026, 149 were still open on October 11.
For Final permits, the median time from issue to completion ranged from 31 days for those issued in 2020 to 88 days for 2011; for 2025 it was 45 days.
These are citywide figures.
Does an expired permit mean the repair failed?
The record cannot tell you. It holds a status and dates, with no reason, so an expired permit does not show whether the work was done or how well.
Of the 1,359 expired permits in this study, 935 (68.8%) expired 180 or 181 days after they were issued. The City words its current rule two ways. Its Homeowner's Permit page says: "Once a permit is activated, it expires on the 181st day if the project has not been scheduled nor received an inspection." Its Activating a Permit page says: "Permits will expire 180 days after activation if the City has not performed an on-site inspection (Pass or Fail)." The Homeowner's Permit page adds that a passing inspection extends the expiration date by 180 days. These are the current rules; we did not check the rules in force in earlier years.
The same page says the contractor listed on a permit may be able to reactivate it through the City's online portal.
Expired permits stay with the house. The Homeowner's Permit page says: "As the property owner, you are responsible for addressing all expired permits, including expired permits performed by previous owners."
What does the reported valuation show?
All but three permits in the study carry a reported valuation. The City's dataset describes the field as "Total dollar valuation for entire job for each building permit". It is the valuation on the downloaded permit record, and the record does not show what a homeowner finally paid.
Before 2021, nearly every permit carried a dollar figure: 6,575 of the 6,611 issued from 2009 through 2020 (99.5%) reported $100 or more. March 2021 was the first month in which most permits listed $1 or less: 34 of 53, against 2 of 47 in January 2021. By June 2021, all 32 did. From January 2022 through September 2026, 3,035 of 3,197 permits (94.9%) list exactly $1.
The records do not say why. The City's current residential fee schedule, for fiscal year 2026-27, does not mention valuation; it sets plan review fees by category and square footage, and it says nothing about 2021.
The table below gives the median reported valuation for each year through 2021, counting only permits that list $100 or more. Dollar figures are not adjusted for inflation.
| Year | Permits at $100 or more | Median reported valuation |
|---|---|---|
| Full year 2009 | 403 | $6,200 |
| Full year 2010 | 482 | $5,650 |
| Full year 2011 | 599 | $5,365 |
| Full year 2012 | 702 | $5,000 |
| Full year 2013 | 576 | $5,200 |
| Full year 2014 | 614 | $5,000 |
| Full year 2015 | 571 | $6,050 |
| Full year 2016 | 569 | $7,000 |
| Full year 2017 | 589 | $7,000 |
| Full year 2018 | 553 | $6,480 |
| Full year 2019 | 505 | $6,300 |
| Full year 2020 | 412 | $7,313 |
| Full year 2021 | 165 | $7,325 |
The 2021 median rests on 165 permits, those listing a reported valuation of $100 or more.
From January 2024 through September 2026, 130 permits list $100 or more, about 6% of the 2,077 issued. Their median is $11,300. The records do not say why these few list $100 or more, so their median cannot stand for the permits listed at $1.
For what repairs cost in Austin, see our Austin cost page, which compares the prices companies publish and engineering evaluation fees.
What the records cannot show
- Work done without a permit.
- Small repairs the City exempts from a building permit, when no permit was issued for them.
- Permits from other cities; the data covers City of Austin permits only.
- Why a permit expired, and whether its work was done or how well.
- What a homeowner paid.
- Exactly what work each permit covered beyond its short description; a few permits that mention the foundation describe other work.
- Where things stand after October 11, 2026: changes to the 157 Active and 3 Pending Permit records may change these figures.
How to use a permit record
- Hiring a company. Ask for the permit number before work starts and look it up yourself. Our questions guide explains who pulls the permit and links Austin's public permit search.
- Comparing companies. Most permits name a contractor company: 96.6% of those issued 2009 to 2020 and 98.3% of those issued since 2024. Our Austin comparison shows, for each listed company, the City permits since 2024 we matched to it, if any, and how many have closed.
- Buying a house. Look up the permits on the property and ask the seller about any marked Expired, since the City holds the owner responsible for them. If a permit expired, ask the seller or the contractor listed on it whether the work was finished and whether the permit can be reactivated.
- Pricing a repair. Leave a permit's reported valuation out of your price comparison, and compare bids priced against the same repair plan.
How we counted
The data is the City of Austin's Issued Construction Permits dataset (3syk-w9eu), published by the Development Services Department on the City's open data portal as public domain and downloaded on October 11, 2026. We selected residential building permits in the Repair work class whose description contains the word foundation; 10,593 records matched.
We left out 192 permits issued before 2009 and 40 issued in October 2026, a month not yet complete. No year before 2009 holds more than 135 permits, and every year from 2009 holds at least 404; we did not check why. That leaves 10,361 permits. Of those, 10,298 are in Austin's full-purpose jurisdiction, 32 in its two-mile extraterritorial jurisdiction, 30 in its limited-purpose area and 1 in Lakeway's extraterritorial jurisdiction; all are kept. Void, withdrawn, cancelled and aborted permits stay in the counts except where a column says otherwise.
Statuses and dates are as of October 11, 2026. The final share of closed permits is Final permits divided by Final plus Expired permits, for all permits together. Percentages are rounded to one decimal place, and dollar figures are nominal.
We compared this download with one taken on October 7, 2026 of permits issued since January 2024. Among permits issued January 2, 2024 through October 6, 2026, none had been added or removed, no valuation had changed, and 11 statuses had changed: 10 from Active to Final and 1 from Active to Expired. The 13 new records were issued October 7 to 9.
How this page works
This page counts City of Austin permit records downloaded on October 11, 2026, and quotes City pages read the same day. It names no company and gives no figure for any company. It describes changes in the numbers without suggesting a reason. No company paid to appear here. The research was done with AI help, and the figures were checked against the City data.

Sources
- City of Austin, Development Services Department, Issued Construction Permits (dataset 3syk-w9eu), checked October 11, 2026
- City of Austin, Work Exempt from Building Permits, checked October 11, 2026
- City of Austin, Express Permits, checked October 11, 2026
- City of Austin, Homeowner's Permit, checked October 11, 2026
- City of Austin, Activating a Permit, checked October 11, 2026
- City of Austin, FY 2026-27 residential fee schedule, checked October 12, 2026